Over the Month of April, collection system cable installation was completed, and majority of foundations were completed. The site roads continue to be improved, and construction on the project substation has begun. Asphalt repairs on West Bear Swamp and Center Roads continue, and remaining areas of the site being continued to get prepped for the start of deliveries to site at the beginning of June. Vestas continues to deliver components to the River Bulk terminal in anticipation of the start of deliveries.