Construction Update - July 2024

During June, Timbermill Wind achieved a major milestone with the first turbine being completely erected. Six towers were completely erected last month and components were delivered to 40% of all sites. Work on the project substation also progressed, with nearly all foundations complete and the setting of steel and equipment well underway.

Looking ahead to July, the permanent Meteorological Evaluation Tower (MET) will be installed, transmission line installation will begin, and wind turbine installation will continue, generally working from North to South through the project area.