Construction Update: February 2024

Currently, crews are furnishing and installing roads, foundations, and collector systems. All equipment, materials, and tooling required to complete the referenced activities are on-site or in delivery. Backfill of the completed foundations will start in the month ahead in preparation for turbine deliveries at the end of May. This month, the on-site workforce was 167 employees, including subcontractors, contractors, and client representatives.